TeraWulf Muskie Data Campus
AI dedicatedOperated by TeraWulf · Ashland, KY, US1 srcupdated 5d ago
Acquired by TeraWulf from Industrial Equity Partners and announced 26 May 2026 as the Muskie Data Campus, a hyperscale HPC/AI development site inside the 1,000-acre EastPark Industrial Park in northeastern Kentucky, with roughly 285 acres owned and controlled. TeraWulf expects the site to support more than 1 GW over time, with an initial 500 MW ramping from the second half of 2028 and a further 500 MW targeted for the second half of 2030. Kentucky Power (AEP) is building a 345 kV substation tied to the existing 765 kV network. The site is already zoned; permitting is under way. Coordinates are city-level for Ashland, Kentucky; the exact parcel is not disclosed.
Compared to peers
Compared with 166 peer facilities in US.
- Capacity (MW)
- 1,0005×+ above median
- median 26 · p95 1,800
- Supplier coverage
- 0no peers
- median 0 · p75 0
- Announce → online lag
- in progress
- no completions yet
Bands describe deviation from peer median; not a judgment.
Ownership chain (TeraWulf)
No ownership chain tracked yet for this entity. Investigators can add parent companies via the ownership_edge table or community findings.
Public subsidies & incentives
No subsidies, tax abatements, or public incentives recorded for this facility yet.
Permits
No permits tracked for this facility yet. Public records (county permits, environmental filings, grid interconnect filings) can be sourced via community findings.
Timeline
- Announced
- —
- Groundbreak
- —
- Online
- —
- Full capacity
- —
Power
- Primary source
- grid-mixed
- Utility
- AEP Ohio
- PUE pledged
- —
Suppliers (0)
No suppliers tracked yet. Sign in to contribute.
Sources (1)
Community findings (0)